How to Install, Sand & Finish Engineered Floors, Part 1: Subfloor Prep

Avi Hadad Headshot
6 24 26 Removing Leveling Compound

6 24 26 Removing Leveling CompoundMost people would refer to the house we are working on as “high-end.” Why? I don’t know. It’s just big and expensive. Nothing is solid, square, flat or parallel. Oh, and the entire house has cheap laminate floors and carpets.

The house is built on the side of a hill with the closest part to the hill on a concrete slab and the suspended areas with a very-out-of-flat OSB subfloor (so we have on-grade and above-grade subfloors). There used to be a lot of leveling compound where the concrete and the OSB meet. The client asked me to install unfinished maple flooring with some borders, diagonal fields, a medallion and inserts in the hallway. Well, I had him choose the wood from samples I had provided but as to the rest, it was a result of our long and detailed consultation. Thanks again to the NWFA, the staff, all the instructors, students and friends I acquired over the years who taught me a lot. I probably spent four to five hours total on selling this job before I got it. It takes a little longer to sell a job like this when the other four contractors are cheaper and don’t grind and seal the concrete! In the end training, education and experience win over just experience.

Step 1: Remove and haul away baseboards and laminate floors. Oh my God (and yes, like California style: oh my Gooood) the baseboards were mitered around the radius outside corners. We will fix that later in this project. Once the demo was completed, we discovered multiple areas with leveling compounds. I tapped with a wooden piece on those areas and found them to be loose. We used hammers, scrapers and grinders to remove the loose areas. We then used grinders to profile the concrete for epoxy (in this case, “profiling” is not wrong!) moisture barrier application. We sprayed the slab with water as we were grinding to minimize silica dust in the air, used proper respirators and HEPA-filtered vacuums attached to all machines.

6 24 26 Grinding Reveals Slab NewStep 2: Now that the slab was free of paint, sealers and whatever else was on it, we were ready to seal any cracks and holes with the proper leveling compound. We vacuumed and used a dry mop to remove any dust and then applied the compound. We let it dry overnight, then buffed the floor with a 100 screen, vacuumed and tacked again. We used a two-part epoxy designed for sealing concrete floors. It was part of a system, so the sealer was compatible with the adhesive we were going to use. It is important to understand that the epoxy has a green-grab time limit, and it is usually up to 36 hours. After that you have to mechanically scratch it with a buffer for the glue to adhere.6 24 26 Filling Slab Cracks

We had to use door skin and 30-pound roofing felt to feather the OSB areas where they met the concrete.

Compared to the other contractors, we probably added a good amount of time to the job in preparation and moisture control alone. In my opinion, all this work is not an option and must be done to guarantee a successful installation. I don’t care that in some cases according to the Guidelines a moisture barrier is not a must. I seal the slab on every job.

[Read Part 2 of this series here]

Page 1 of 13
Next Page
Resource Book
Looking for a specific product or a company? Wood Floor Business has the only comprehensive database of the industry.
Learn More
Resource Book
Podcasts
All Things Wood Floor, created by Wood Floor Business magazine, talks to interesting wood flooring pros to share knowledge, stories and tips on everything to do with wood flooring, from installation, sanding and finishing to business management.
Learn More
Podcasts